Information on this page is for customers in 

{{ town-name }}

Andrew Square to Dewar Street Reliability Project

Why Are We Doing This Project?

To improve the reliability of Boston’s electric system now and into the future, a new 2.1 mile underground 115-kilovolt (kV) transmission line will connect Eversource's Andrew Square substation to the Dewar Street substation.

The project also includes improvements within the existing fence lines of our substations, to further ensure the delivery of safe, reliable power.

Where Is This Work Being Done?

The 2.1-mile transmission line will run under streets in Dorchester and South Boston, connecting our Andrew Square and Dewar Street substations.

View an interactive Google map that shows estimated locations of manholes and duct bank that will be installed during the construction of this project.

When Is The Work Being Done?

  • Start of construction*Second Quarter 2022
  • Projected in-service date*: Fourth Quarter 2024

* Pending all necessary siting and permit approvals

Construction Updates

We are committed to keeping neighbors, businesses and community members informed on project activities during construction. The schedule may change due to weather or other unexpected circumstances.

Please follow all local detour and traffic signage to move safely around work zones.

Andrew Square Substation

Week of September 16

  • Crews plan to continue work at the Andrew Square substation located along Ellery Street. This work consists of forming and altering the foundation of the control house site, performing survey tests, and continued electrical work within the substation property. Equipment that may be needed to complete this activity includes excavators, front-end loaders, concrete cutting saws, and jackhammers.
  • All contractor vehicles will be parked inside the substation fence.
  • Continuing on Monday, September 16, crews will be mobilized on Boston Street, just outside the Andrew Square Substation, to perform test pits.
  • Equipment needed to complete this work includes jackhammers, concrete cutting saw, vacuum truck, and dump trucks.

All work will be contained within a temporary work on the southbound parking lane and sidewalk of Boston Street.

Mary Ellen McCormack

Week of September 16

O’Callaghan Way

  • Crews will be mobilizing to O’Callaghan Way, inside the Mary Ellen McCormack Community, between Gavin Way and Old Colony Avenue, continuing the week of September 16, working to perform test pits and excavate duct-bank.
  • Crews will also continue duct bank excavation work on the grass lawn at the intersection of O’Callaghan Way and Kemp Street.
  • Equipment needed to complete this work includes a concrete cutting saw, jackhammers, excavators, and dump trucks.
  • All work will be conducted between the permitted hours of 7 a.m. to 4 p.m., Monday through Friday.

All work will be contained within temporary work zones along O’Callaghan Way. 

There will be 'No parking' signs posted along O’Callaghan Way the length of the work zone: there will be no parking allowed in these spots during daytime work hours. Police details have been requested to assist with traffic management during the use of the construction work zone.

All work will be contained within temporary work zones along Kemp Street. Thru traffic will be facilitated during this work along Kemp Street.

There will be 'No parking' signs posted along the intersection of Kemp Street and O'Callaghan Way, the length of the work zone. There will be no parking allowed in these spots during daytime work hours. Police details have been requested to assist with traffic management during the use of the construction work zone.

Morissey Boulevard

Week of September 16

There will be no work on Morrisey Boulevard this week.

    Savin Hill

    Week of September 16

     

    Grampian Way

    • Crews will be mobilizing to Grampian Way outside the Basketball Courts at Savin Hill Park continuing on Monday, September 16.
    • Crews will begin excavating for, and then install, a new electric manhole.
    • Equipment needed to complete this work includes a concrete-cutting saw, excavator, jackhammers, dump trucks, and a vacuum truck.

    Traffic management: A temporary work zone will be setup along Grampian Way from the Evandale Terrace intersection to the Tennis Courts at Savin Hill Park. This will be a full road closure; no vehicles will be allowed to pass through.

    All traffic will be diverted through the northern portion of Grampian Way. No parking signs will be posted along the length of the coned-off work zone. There will be No Parking in these spots during daytime work hours.

    Springdale Street

    Trenching/conduit installation and restoration activities are scheduled to continue and last the duration of the week. 

    Dewar Street Substation

    Week of September 16

    Crews plan to continue work at the Dewar Street substation located near 65 Bay Street. This work consists of forming and altering the foundation of the control house site, performing survey tests, and continued electrical work within the substation property.

    Equipment that may be needed to complete this activity includes excavators, front-end loaders, concrete cutting saws and jackhammers.

    All contractor vehicles will be parked inside the substation fence.

    Traffic Management Plans

    Working in consultation with town and state officials, including the Massachusetts Department of Transportation, we developed a traffic management plan (TMP) for each section of the project.

    The TMPs include a detailed site plan, hours of construction and area-specific traffic controls.

    All TMPs are subject to change and may be updated often.

    Siting Review

    We filed a petition with the Massachusetts EFSB for approval to construct and operate the new 115-kV transmission line.

    The petition filing is part of the regulatory review process, as defined by Massachusetts state statutes.

    On March 1, 2019, we submitted the following Siting Petition to the EFSB:

    The EFSB held a Public Comment Hearing on June 26, 2019, in Boston, where individuals and groups affected by the initial petition were given the opportunity to voice feedback to the Siting Board.

    The Siting Board conducted a remote Siting Board meeting using Zoom on June 30, 2021, at 1 p.m. to listen to comments and vote on whether to approve, approve with conditions or reject the project.

    The Siting Board's Final Decision to approve the project was issued on July 2, 2021.

    Community Outreach

    We're committed to engaging city officials, residents, businesses, community groups and other stakeholders about project activities through municipal briefings, mailings, virtual meetings and door-to-door outreach, while adhering to COVID-19 social distancing and other related health and safety guidelines.

    Sign up for weekly updates here.

    Have Questions?

    Keeping the lines of communication open is an important part of our work in your community.

    For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.