Information on this page is for customers in 

{{ town-name }}

Cape Cod Solution Phase 1: Mid-Cape Reliability

Why Are We Doing This Project?

This project is the first phase of the Cape Cod Solution Program, a group of projects designed to improve the reliability of the electric system serving the Southeastern Massachusetts and Greater Cape Cod areas both today and in the future as more clean energy resources like offshore wind are connected to the grid.

Join the email list for regular construction and community updates

Where Is This Work Being Done?

The new line will be constructed between the Bourne Switching Station and West Barnstable Substation. This project also includes an expansion of the western side of the West Barnstable Substation.

The approved route runs approximately 13 miles within an existing right of way (power line corridor), passing through portions of Bourne, Sandwich and Barnstable.

* Click to Enlarge

Traffic Management Plans

When Is The Work Being Done?

  • Start of construction: Q1 2023
  • Projected in-service date: Q2 2024

*Subject to change

About this project

  • Route length: 13 miles
  • Line voltage: 115,000-volt (115-kV) transmission line
  • Siting review by: Energy Facilities Siting Board (EFSB)
  • Public Open Houses: July 29 and 30, 2019
  • EFSB Approval: December 16, 2022

Construction Updates

Bourne

All work in Bourne takes place in the power line corridor within Joint Base Cape Cod.

Crews will mow the power line corridor to prepare for access installation from the Bourne Station east to the West Barnstable Station on Oak Street over the next few weeks.

Week of May 29

  • Crews continued to install access to and establish level work areas around structure locations using temporary construction matting or gravel.
  • Crews continued the installation of structure foundations.

Week of June 5

Crews intend to continue the installation of structure foundations.

Sandwich

Crews will be mowing the power line corridor to prepare for access installation working from the Bourne Station east to the West Barnstable Station on Oak Street over the next few weeks.

Week of May 29

Between Route 130 and Quaker Meetinghouse Road

Crews continued to install distribution poles.

Between Mill Road and Great Hill Road

  • Crews continued to install distribution poles.
  • Crews installed access to and established level work areas around structure locations using temporary construction matting or gravel.

Week of June 5

Between Route 130 and Quaker Meetinghouse Road

  • Crews intend to begin the installation of structure foundations.
  • Crews intend to continue installing distribution poles. 

Between Quaker Meetinghouse Road and Mill Road

Crews intend to continue to install distribution poles.

Between Mill Road and Great Hill Road

  • Crews intend to continue to install distribution poles.
  • Crews intend to continue to establish work areas around structure locations.

Barnstable

Crews will be mowing the power line corridor to prepare for access installation working from the Bourne Station east to the West Barnstable Station on Oak Street over the next few weeks.

Week of May 29

Between Barnstable Town Line and Route 149

  • Crews installed access to and established level work areas around structure locations using temporary construction matting or gravel.
  • Crews installed distribution poles.

Week of June 5

Between the Barnstable Town Line and Route 149

  • Crews intend to continue to install access to and establish level work areas around structure locations using temporary construction matting or gravel.
  • Crews intend to continue installing distribution poles.

Between Route 149 and Oak Street

Crews intend to install access to and establish level work areas around structure locations using temporary construction matting or gravel.

 

Siting Review

On November 8, 2019, we filed the below documents with the EFSB for approval to construct and operate the new transmission line: 

Through the EFSB process public and other interested stakeholders were given the opportunity to participate through the EFSB-sponsored public hearing. Owners of property abutting and near the project were informed of the EFSB Public Comment Hearing held virtually on June 10, 2020. 

The EFSB conducted a remote Siting Board Meeting via Zoom on Thursday, December 15, 2022, at 1 p.m. to vote on whether to approve, approve with conditions or reject the project. The EFSB’s Final Decision to approve the project was issued on December 16, 2022.

To learn more about the siting process and how to participate, visit the EFSB website.

Community Outreach

We will continue to engage with town officials, residents, businesses, community groups and other stakeholders through municipal briefings, door to door outreach, site visits, and addition meetings as needed – answering questions and listening to concerns about the project. We will also maintain an active field presence during construction.

On May 18 we hosted key stakeholders, including state and local officials, at our Bourne Substation on Joint Base Cape Cod to celebrate the groundbreaking of phase one of the Cape Cod Solution.

Have Questions?

Keeping the lines of communication open is an important part of our work in your community.

For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.