Information on this page is for customers in 

{{ town-name }}

Martha's Vineyard Reliability and 91 Cable Replacement Projects

 Português Brasileiro (PDF)

Why Are We Doing These Projects?

Both of these new lines will interconnect to existing substations in the area and will bolster system capacity and reliability on Martha's Vineyard to meet growing energy needs.

These projects will also help facilitate our efforts to decrease our carbon footprint by decommissioning the five existing diesel generators on the Island.

Email updates

Sign up for regular updates about construction and community outreach in your area.

Sign up for Falmouth emails Sign up for Martha's Vineyard emails

Where Is This Work Being Done?

Both projects will go through Falmouth and will come onshore to Martha's Vineyard in Oak Bluffs and Tisbury.

marthas-vineyard-91-projects-falmouth

The work will be done in Falmouth and Martha's Vineyard (Tisbury and Oak Bluffs).

Martha's Vineyard Reliability Project

The proposed project will include the installation of a new 2.7 mile underground manhole (precast concrete vault) and duct bank system (a series of conduits that house electric cables).

The proposed route runs from the existing Falmouth Station on Stephens Lane to Jones Road, onto the Shining Sea Bikeway, down Mill Road to Surf Drive before transitioning in the Surf Drive parking lot to a submarine cable to cross Vineyard Sound.

The line will then travel 6.1 miles buried in the sea floor of Vineyard Sound before landing at East Chop, on Eastville Avenue where it will transition to onshore cables.

Once onshore, the line follows a new duct bank and manhole system along Eastville Avenue to an Eversource parcel.

marthas-vineyard-reliability-oak-bluffs

The project will also include upgrades to the Falmouth Substation to support the installation of the new line and the installation of six pad-mounted transformers at the Eastville parcel to facilitate distribution of the new electric line feeding the Island.

91 Cable Replacement Project

The proposed project will follow the same duct bank and manhole system as the Martha’s Vineyard Reliability Project but will terminate at the Mill Road parking lot before transitioning to a 5.5 mile submarine cable to cross the Vineyard Sound and land at Eversource facilities in West Chop.

91-cable-tisbury


When is the Work Being Done?

  • Public open houses: Spring 2022
  • File environmental notification form for review under the Massachusetts Environmental
  • Policy Act (MEPA): May 2022
  • Start of construction: December 2023
  • Estimated in-service date: March 2026

About These Projects

Martha's Vineyard Reliability Project

  • Falmouth: approx. 2.7 miles
  • Vineyard Sound: approx. 6.1 miles
  • Oak Bluffs: approx. 0.3 miles
  • Line voltage: 23kV

91 Cable Replacement Project

  • Falmouth: approx. 2.7 miles
  • Vineyard Sound: approx. 5.5 miles
  • Line voltage: 23 kV

Construction Updates

We are committed to keeping neighbors, businesses and community members informed on project activities during construction. The schedule may change due to weather or other unexpected circumstances.

Week of May 19

Martha’s Vineyard

Next week, restoration will continue in Oak Bluffs and Tisbury. 

In Oak Bluffs:

  • Crews will continue to access the Eversource-owned parcel on Eastville Avenue. Please be aware of trucks entering and exiting the property. 
  • Crews will restore the construction zone at the 5th cable landing site.

In Tisbury, crews will restore the construction zone at the 91-cable landing site.   

Approved work hours for activities in Martha's Vineyard are Monday through Saturday, 7 a.m. to 5 p.m.

Falmouth

Next week, crews will continue restoration of Surf Drive between Mill Road and Shore Street. 

Community Outreach

We're committed to partnering with all community members, municipal leaders and other interested stakeholders to provide more information on the projects, gather feedback and answer any questions or concerns.

Public open houses were held both in-person and virtually in each host community in the spring of 2022.

Have Questions?

Keeping the lines of communication open is an important part of our work in your community.

For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.