Information on this page is for customers in
{{ town-name }}
UCMP Springfield Line 1322
Español (PDF)
Why Are We Doing This Project?
As part of our ongoing commitment to deliver reliable energy and superior service to our customers, we are proposing to replace an existing 115-kilovolt (kV) high pressure fluid-filled (HPFF) underground transmission line in the Greater Springfield area. The existing transmission line was installed in 1955, is nearing the end of its design life expectancy and needs to be replaced.
The proposed transmission system improvements proactively increase system reliability by:
- Proactively addressing any issues obtaining supplies needed for system repairs and upgrades
- Upgrading to a system technology with longer life expectancy
- Reducing occurrence of unplanned outages which may require the need for emergency replacement or repair
- Eliminating the risk of oil leaks from existing HPFF cables
- Potentially increasing line capacity for future load growth
The proposed project is part of a larger program we are conducting throughout our service territory in Connecticut and Massachusetts called the Underground Cable Modernization Program (UCMP). This program is designed to modernize and increase the capacity of the existing underground transmission cable systems by replacing existing HPFF with cross-linked polyethylene cable (XLPE). This project also aligns with helping Massachusetts achieve its net-zero carbon emissions goal by 2050.
Where Is This Work Being Done?
See Figure 2 for a graphical depiction of all initially considered project routes. A thorough review of this list is underway and will determine which routes remain viable options. Local municipality and neighborhood groups are involved and providing feedback throughout the review process.
In the Springfield and East Springfield area, one of the proposed projects includes the rebuild of a 2.8 mile 115-kV underground electric transmission line connecting the existing Breckwood and East Springfield substations, both located in Springfield.
The proposed replacement lines will follow the same or similar route whenever possible, under the roadway.
Once all local and state approvals have been received, construction will include excavation for the cable system trench and vault/cable installation. Following completion of construction, we will coordinate with affected municipalities on restoration of affected areas.
Equipment upgrades will be required at the East Springfield and Breckwood substations to accommodate the connection of the XLPE cable. This work will occur within the existing footprint of the stations.
When Is The Work Being Done?
- Massachusetts Department of Public Utilities filing: First quarter 2025
- Start of construction: Second quarter 2028*
- Projected construction completion: Third quarter 2028*
*Dates subject to change, pending all necessary approvals
About this project
- Route length: 2.8 miles
- Line voltage: 115 kilovolts (kV)
Siting Review
This project requires a submission to the Energy Facilities Siting Board (EFSB) and/or the Department of Public Utilities (DPU). We intend to submit its filing in the first quarter of 2025. Environmental permits will also be required from local, state and federal agencies.
Community Outreach
We are committed to engaging city officials, residents, businesses, community groups and other interested stakeholders about the project through meaningful engagement. Our team strives to incorporate local feedback as feasible. Project team members will remain engaged with the community throughout the project to provide updates on the schedule and address questions and concerns.
Below is a summary of past outreach activities.
- Open house event at Springfield Central High School cafeteria (March 27, 2024)
- Pop up event at IronMan Expo at MassMutual Center (June 7-8, 2024)
- Open house event at Springfield Central High School cafeteria (September 4, 2024)
Have Questions?
Keeping the lines of communication open is an important part of our work in your community.
For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.