Information on this page is for customers in
{{ town-name }}
Greater Cambridge Energy Program (GCEP)
Why Are We Doing This Project?
The Greater Cambridge area is experiencing a surge of new residential and commercial development that, along with goals of reduction of fossil fuels in new buildings and electrification, is generating a growing demand for power.
This first-of-its-kind transmission initiative is innovatively designed to place a significant amount of needed infrastructure underground and out of sight, becoming the largest underground substation in the country at 35,000 square feet.
This project will address the increased electric demand in the region, enhance the resiliency of the transmission system and ensure a flexible grid to reliably serve customers while supporting the decarbonization and electrification goals of both the City of Cambridge and Massachusetts to lessen the impact of climate change.
Where Is This Work Being Done?
The new underground substation will be located between Broadway and Binney Street in Kendall Square and will be integrated into a large mixed-use development project at the former Kendall Center Blue Garage site.
This project will include five underground duct banks housing eight new 115-kilovolt (kV) transmission lines. The transmission routes will span Boston (Allston/Brighton), Cambridge, and Somerville interconnecting to existing substations in these communities.
A partnership spearheaded by City of Cambridge officials, Eversource and BXP yielded this collaborative effort to uniquely locate the substation underground — a first of its kind in the country. Where there was once a parking garage above ground, there will be an open and accessible outdoor public community space.
Rendering of the underground substation.
EFSB approved routes:
When Is The Work Being Done?
- File siting petition with the Energy Facilities Siting Board (EFSB): March 10, 2022 (Initial Petition, Volume 1, Volume 2, Volume 3)
- EFSB public hearing: June 28, 2022, November 10, 2022
- Final decision from the EFSB: June 28, 2024
- Start of construction: Q1 2025*
- Estimated in-service dates: Q1 2029*
- Construction completed: 2031*
*Dates subject to change
Additional information can be found on the Siting Board's website and on our project fact sheet.
Construction Updates
We're committed to keeping neighbors, businesses and community members informed on project activities during construction. You can sign up to receive email updates like the ones below:
Information Available in Additional Languages
Español (Spanish)
- Ficha del proyecto - Project Fact Sheet
- Presentación de la reunión abierta al público de octubre de 2021 - October 2021 Open House Meeting Presentation
- Presentación de Eversource y la ciudad de Cambridge sobre las novedades del proyecto el 4 de octubre de 2023 - Presentation from Eversource and the City of Cambridge on the project news on October 4, 2023
- Presentación de audiencia pública del 10 de noviembre de 2022 - Public Hearing Presentation, November 10
- Audiencia pública complementaria del 10 de noviembre de 2022- Supplemental Notice of Adjudication and Public Comment Hearing, November 10, 2022
- Resumen de la audiencia pública complementaria del 10 de noviembre de 2022 - Summary of the November 10, 2022 Supplemental Public Hearing
- Presentación de audiencia pública del 28 junio de 2022 - Public Comment Hearing Presentation, June 28, 2022
- Notificaciones de audiencias públicas - Public Comment Hearing Notification
- Resumen de notificación complementaria de resolución y audiencia pública - Public Comment Hearing Notification Summary
Kreyòl Ayisyen (Haitian Creole)
- Fich Teknik Pwojè a - Project Technical Sheet
- Oktòb 2021 Prezantasyon Reyinyon Pòt Louvri a - October 2021 Open House Presentation
- 4 Oktòb 2023 Prezantasyon sou Mizajou Pwojè Eversource ak Vil Cambridge la - October 4, 2023 Project Presentation, Eversource Update with the City of Cambridge
- Prezantasyon Odyans Kòmantè Piblik - Public Comment Hearing Presentation, November 10, 2022
- Odyans Kòmantè Piblik Konplemantè nan dat 10 Novanm 2022 - Supplemental Notice of Adjudication and Public Comment Hearing, November 10, 2022
- Rezime Odyans Kòmantè Piblik Konplemantè nan dat 10 Novanm 2022 - Supplemental Notice of Adjudication and Public Comment Hearing Summary, November 10, 2022
- Prezantasyon Odyans Kòmantè Piblik - Public Comment Hearing Presentation, June 28, 2022
- Avi pou Odyans Kòmantè Piblik - Notice for Public Comment Hearing
- Rezime Avi pou Odyans Kòmantè Piblik - Summary Notice for Public Comment Hearing
Português (Portuguese)
- Ficha Técnica do Projeto - Project Fact Sheet
- Apresentação para a Reunião Open House de outubro de 2021 - Presentation for the October 2021 Open House Meeting
- Apresentação de Atualização do Projeto da Eversource e da Cidade de Cambridge em 4 de outubro de 2023 - Eversource and City of Cambridge's Project Update Presentation on October 4, 2023
- Apresentação da Audiência para Comentários Públicos - Presentation of the Hearing for Public Comment
- Audiência Suplementar para Comentários Públicos de 10 de novembro de 2022 - November 10, 2022 Public Comment Supplemental Hearing
- Resumo da Audiência Suplementar para Comentários Públicos de 10 de novembro de 2022 - Summary of the November 10, 2022 Supplemental Hearing for Public Comment
- Apresentação da Audiência para Comentários Públicos - Presentation of the Hearing for Public Comment, June 28, 2022
- Notificação da Audiência para Comentários Públicos - Notice of Hearing for Public Comment
- Resumo da Notificação da Audiência para Comentários Públicos - Summary of Notice of Hearing for Public Comment
中文(普通话)(Chinese Mandarin)
- 项目情况说明书 - Project Fact Sheet
- 2021年10月公众开放日会议介绍 - Presentation of the October 2021 Open to the Public Day meeting
- 2023年10月4日Eversource和剑桥市项目最新情况介绍 - October 4, 2023 Eversource and Cambridge City Project Update
- 公众意见听证会介绍 - Public Comment Hearing Presentation, November 10, 2022
- 裁决和公众意见听证会补充通知- Notice of Decision and Public Comment Hearing Supplement
- 裁决和公众意见听证会补充通知摘要 - Summary of Supplemental Notice for Ruling and Public Comment Hearing
- 公众意见听证会介绍 - Public Comment Hearing Presentation, June 28, 2022
- 公众意见听证会通知 - Public Comment Hearing Notification
- 公众意见听证会通知摘要- Notice of Public Comment Hearing Summary
Community Outreach
We're committed to continuing our collaborative working partnership with each local community, municipal leaders and other interested stakeholders.
Our public outreach efforts began in 2019 and we held our first public open house in 2021. We will continue to engage and solicit feedback from a diverse cross-section of neighborhoods that the project will traverse.
City officials, residents, businesses, community groups and other stakeholders will be kept informed about project happenings and activities through municipal briefings, mailings, virtual meetings, in-person meetings, constant contact and door-to-door outreach.
Upcoming Opportunity
We're hosting an open house where you can ask questions and learn more about the project before construction begins in early 2025. Printable event flyer (PDF)
Tuesday, October 22 from 5:30-7:30 p.m.
355 Main Street | Cambridge, Massachussets
2023
- Eversource and City of Cambridge project update - Meeting invite | Presentation (October 4)
2022
Supplemental Public Comment Hearing (November 10)
- Public Comment Hearing Presentation
- Supplemental Notice of Adjudication and Public Comment Hearing
- Supplemental Notice of Adjudication and Public Comment Hearing Summary
Public Comment Hearing (June 28)
Public Hearing Notifications
2021
- Open house meeting presentation - Cambridge | Allston-Brighton | Somerville (October)
- Open house invites - Cambridge | Allston-Brighton | Somerville (October)
Have Questions?
Keeping the lines of communication open is an important part of our work in your community.
For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.