Blandford Substation Upgrade

Why Are We Doing This Project?

We determined after an extensive study that integration of additional clean energy into the electrical grid in the Plainfield-Blandford area requires upgrades to our Blandford Substation. This project will support interconnection of new renewable resources and improve reliability.

This work is part of a larger initiative focused on electric system enhancements to maintain reliability and enable distributed energy resource (DER) facilities to safely interconnect and operate.

Where Is This Work Being Done?

*Click map to enlarge

The substation is located on North Blandford Road. Upgrades to the substation include:  

  • Expanding the fenced substation yard on our property from approximately 0.65 acres to approximately 1.13 acres to accommodate new equipment 
  • Replacing two existing transformers
  • Installing new foundations, trenching and conduits
  • Installing a new switchgear enclosure
  • Installing two new circuit breakers 
  • Installing a new chain link mesh fence, of similar height to existing
  • Constructing a new access driveway off North Blandford Road

    When Is The Work Being Done?

    • Proposed start of construction: Q1 2027*
    • Estimated in-service date: Q1 2028*
    • Construction duration: Approximately 12 months*

    *Subject to change, pending necessary approvals

    Siting Review

    Dates

    • Petition filing with Energy Facilities Siting Board (EFSB): June 23, 2025
    • EFSB public hearing: TBD
    • Petition decision from EFSB: TBD

    Documents

    Visit the EFSB website for project filing information.

    Community Outreach

    We are committed to engaging city officials, residents, businesses, community groups and other interested stakeholders about the project through meaningful engagement. Our team strives to incorporate local feedback as feasible. Project team members will remain engaged with the community throughout the project to provide updates on the schedule and address questions and concerns.  

    Have Questions?

    Keeping the lines of communication open is an important part of our work in your community. We welcome input from the community.

    For more information about this project, please call the project information hotline at 833-836-0302 or email ProjectInfoMA@eversource.com.