Information on this page is for customers in
{{ town-name }}
Carver to Kingston Reliability Project
Why Are We Doing This Project?
This upgrade is one of a group of projects designed to improve the reliability of the electric system serving southeastern Massachusetts, both today and in the future.
Where Is This Work Being Done?
The proposed new line would be constructed between our Carver Substation and our Kingston Substation.
The preferred solution runs approximately 8 miles within a right of way (power line corridor), passing through portions of Carver, Plympton and Kingston.

* Click to Enlarge
When Is The Work Being Done?
- Start of construction: First Quarter 2022
- Projected in-service date: June 2023
About this project
- Route length: 8 miles
- Line voltage: 115,000-volt (115-kV) transmission line
- Siting review by: DPU
Construction Updates
We're committed to keeping neighbors, businesses and community members informed on project activities during construction.
Construction began in 2022 and work is not expected to interrupt electric service to homes or businesses.
Kingston
Week of May 1
No work is planned to occur within Kingston this week, however, vehicles will be entering and existing the right-of-way from the Brook Street Substation.
Week of May 8
Our contractor, MJ Electric, will work to erect the final few structures within the right-of-way. This work will take place off Deer Run Road, Smith Fuller Way, and Wapping Road.
Additionally, our contractor, MJ Electric, will be preparing the new structures for a rope pulling. This work is to ensure a safe wire pulling at a later date.
Week of May 15
Our contractor, MJ Electric, will be pulling rope and wire between the new structures within the right-of-way. This work is planned to occur between Deer Run Road and Pembroke Street.
Plympton
Week of May 1
No work is planned to occur within Plympton this week, however, vehicles will be entering and existing the right-of-way from the Brook Street Substation.
Week of May 8
Our civil crew, BluRoc, will begin with restoration within the right-of-way. The work will mainly focus on restoring work pads and pull pads. This work will occur from Spring Street towards Kingston.
Week of May 15
Our civil crew, BluRoc, will begin with restoration within the right-of-way. The work will mainly focus on restoring work pads and pull pads. This work will occur from Spring Street towards Kingston.Carver
Week of May 1
Our contractor, MJ Electric, will continue to pull the new line between the new structures. This work will take place off Main Street, Silva Street, Johns Pond Road, Surrey Drive, Center Street, and Plymouth Street.
Week of May 8
Our contractor, MJ Electric, will continue to pull the new line between the new structures. This work will take place off Main Street, Silva Street, Johns Pond Road, Surrey Drive, Center Street, and Plymouth Street.
Week of May 15
Our contractor, MJ Electric, will continue to pull the new line between the new structures. This work will take place off Main Street, Silva Street, Johns Pond Road, Surrey Drive, Center Street, and Plymouth Street.
Siting Review
To construct and operate the proposed transmission line, Eversource must file a petition with the Massachusetts Department of Public Utilities (DPU) for approval. The petition filing is part of the regulatory review process, as defined by Massachusetts state statutes.
On May 6, 2022, we received approval from the DPU to construct the Carver to Kingston Reliability Project. See the DPU 20-67 Final Order.
Related Files
Community Outreach
We're committed to engaging city officials, residents, businesses, community groups and other stakeholders about project activities through municipal briefings, mailings, virtual meetings and door-to-door outreach.
We will continue these outreach efforts as the proposed project proceeds through the siting process and into construction.
Have Questions?
Keeping the lines of communication open is an important part of our work in your community.
For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.