Information on this page is for customers in
{{ town-name }}
Affected System Operator Studies
In coordination with Eversource, ISO-New England has determined transmission studies are needed for many DG projects interconnecting to Eversource's infrastructure.
The Affected System Operator (ASO) studies seek to identify whether a distributed generation (DG) project impacts the transmission system and/or the electric power systems of neighboring electric distribution companies, and the extent transmission system modifications are required to maintain the safe and reliable operation of the region's transmission system and distribution infrastructure.
If modifications are needed, DG projects could share in the cost of that work.
The transmission analysis and studies are being performed by Eversource’s transmission staff, consulting with other affected systems operators, including ISO-New England (ISO-NE). Results of the study need to be approved by ISO-NE.
Analysis requirements
Based on factors such as the size of a generator, operating voltage level and connection with a transmission line, various levels of analysis may be required. Eversource works with ISO-NE to determine the initial level of transmission study needed for each project.
Our goal is to safely and expediently get distributed generation projects up and running as quickly as possible. We are committed to transparency and will work with potential project stakeholders to answer questions and expedite the study process.
As part of D.P.U. 19-55, Eversource and the other Electric Distribution Companies prepared a diagram illustrating the process and decision points for the initial ASO Impact Screen (PDF). This process was created with stakeholder input, including ISO-NE.
Additional information about ASO studies is available on the Department of Public Utilities website under docket 19-55.
DG Guidelines for Interconnection
We have established Distributed Generation Guidelines for Interconnection in collaboration with the Massachusetts Department of Public Utilities (MA DPU). This document:
- Explains the electric distribution company's (EDC) process for screening projects in ASO Impact Screens throughout the application lifecycle
- Details reporting, communications and updates to affected customers during the application process and throughout any ASO study moving forward
Current Phase
The 2021 ASO study announced on March 15, 2021 in the Western Massachusetts and Greater Boston regions has completed.
The 2021 Level 0 studies in Western Massachusetts and Greater Boston have been completed and were approved at the ISO-New England RC meeting in December 2021. The Level 3 study has been completed and were approved at the ISO-New England RC meeting in December 2022.
To be considered for the 2023 ASO study in these areas, submitted applications must be deemed complete by January 31, 2023. New projects in the Western Massachusetts and Greater Boston will be reviewed with ISO-NEW England in preparation for the next ASO in these areas.
The 2021 Level 0 studies in the Southeastern Massachusetts and Cape regions have completed and were approved at the ISO-New England RC meeting in May 2022. The 2021 Level 3 studies in the Southeastern Massachusetts and Cape regions commenced in June 2022 and are underway.
The next round of ASO studies in the Southern Massachusetts and Cape regions will be announced upon the completion of the 2021 Level 3 studies.
Initial Determination Requests
When an ASO Impact Screen results in the potential need for a DG project to undergo an ASO study, Eversource will submit the project’s data to ISO-New England (ISO-NE) with a request for determination on being included in an ASO study. Eversource will post those projects in this section along with any response it receives from ISO-NE.
ASO Maps
View our comprehensive hosting capacity maps for Eastern and Western Massachusetts, including the five ASO study areas: Springfield, Pittsfield, Greater Boston, Upper Southeastern Massachusetts (Upper SEMA) and Cape.
These maps reflect the current status of the ASO studies:
Notifications, FAQs and Important Information
As required by the Department of Public Utilities (DPU), Eversource has reached out via email to developers with projects needing an ASO study. PDFs of the notification are available below. Information shared during the ASO Customer Kickoff Meeting is also linked below in PDF format.
2020 ASO (announced 10/24/19)
Notices and information
All files are in PDF format.
- Eastern Massachusetts - Level 1
- Eastern Massachusetts - Level 3
- Western Massachusetts - Level 1
- Western Massachusetts - Level 3
- Customer Kickoff Meeting Presentation (December 12, 2019)
- ASO Stakeholder Meeting Presentation (February 24, 2020)
- ASO Stakeholder Meeting Presentation (December 11, 2020)
Reports to impacted customers
Every two weeks prior to the study commencing, Eversource reported out to impacted customers. An archive of those reports is available below.
- April 9, 2020
- March 26, 2020
- March 12, 2020
- February 27, 2020
- February 13, 2020
- January 30, 2020
- January 16, 2020
- January 2, 2020
- December 19, 2019
- December 5, 2019
- November 21, 2019
On a monthly basis, Eversource will report out on the status and updates of the ASO studies that we have commenced, until those studies are completed. There is currently one group of ASO customers receiving these monthly reports (customers who are in the Level 3 ASO study announced on October 24, 2019). Previously Level 0/1 ASO study customers and customers who had an interconnection service agreement (ISA) were receiving these reports as well. An archive of those reports is available below.
- Post ISA Customer Monthly Reports
- Level 0/1 ASO Customer Monthly Reports
- Level 3 ASO Customer Monthly Reports
2021 ASO
Notices and information
All files are in PDF format unless otherwise noted.
- 2021 ASO Notification
- 2021 ASO Customer Kickoff Meeting – Greater Boston & WMA
- 2021 ASO Customer Kickoff Meeting – SEMA and Cape
- 2021 ASO Customer Update Meeting – SEMA/Cape Level 0 and Level 3
Reports to impacted customers
Monthly (PDFs)
- April 2023
- March 2023
- February 2023
- January 2023
- December 2022
- November 2022
- October 2022
- September 2022
- August 2022
- July 2022
- June 2022
- May 2022
- April 2022
- March 2022
- February 2022
- January 2022
- December 2021
- November 2021
- October 2021
Biweekly (PDFs)
Every two weeks prior to a study commencing, Eversource will report out to impacted customers.
- February 1, 2023
- January 16, 2023
- January 1, 2023
- December 15, 2022
- December 1, 2022
- November 15, 2022
- November 1, 2022
- October 17, 2022
- October 3, 2022
- September 15, 2022
- September 1, 2022
- August 15, 2022
- August 1, 2022
- July 15, 2022
- July 1, 2022
- June 15, 2022
- June 1, 2022
- May 16, 2022
- May 2, 2022
- April 15, 2022
- April 1, 2022
- March 15, 2022
- March 1, 2022
- February 15, 2022
- February 1, 2022
- January 18, 2022
- January 3, 2022
- December 15, 2021
- December 1, 2021
- November 15, 2021
- November 1, 2021
- October 15, 2021
- October 1, 2021
- September 1, 2021
- August 16, 2021
- August 2, 2021
- July 15, 2021
- July 1, 2021
- June 15, 2021
- June 1, 2021
- May 17, 2021
- May 3, 2021
- April 15, 2021
- April 1, 2021
- March 15, 2021
- March 1, 2021
- February 16, 2021
- February 1, 2021
- January 15, 2021
- Eversource Proposed Study Level Determinations and ISO-NE Comments and Study Level Determinations - Greater Boston Area (.xls file download)| Western Mass Area (.xls file download)| SEMA and Cape Areas (.xls file download)
- Frequently Asked Questions (PDF) - This updated FAQ includes answers to questions asked during the ASO Stakeholder meetings.
- Technical Data Request List for ASO Transmission Studies (PDF)
- Inverter/Design Changes & Customer Required Action (.xls file download) – describes the customer-required follow ups for design changes based on the study phase the project is currently in
- ISO-NE’s role in the Interconnection Process (PDF)
2023 ASO
Notices and information
All files are in PDF format unless otherwise noted.
Western MA and Greater Boston
Reports to impacted customers
Biweekly (PDFs)
Every two weeks prior to a study commencing, Eversource will report out to impacted customers.
Have questions?
If you have questions or would like more information about the ASO study process, please email your account executive.