Information on this page is for customers in 

{{ town-name }}

Woburn to Wakefield Line Project

Why Are We Doing This Project? 

This project improves reliability and addresses the growing need for electricity in the area. We completed our portion of the project in March 2024. The new transmission line was energized and put into service on March 25, 2024. Restoration along the project route will be completed in 2024. You can sign up for routine project construction email updates

Where Is This Work Being Done?

This project included a new 345-kilovolt (kV) underground transmission line that connects Eversource’s Woburn substation and National Grid’s Wakefield Junction substation.

The line extends approximately 8.5 miles between two existing substations, passing through Woburn, Winchester, Stoneham and Wakefield. The project also included improvements within the existing fence lines of the Woburn and Wakefield substations. 

We have constructed the new line from the Woburn Substation through Woburn, Winchester and Stoneham to the Wakefield border. For more information specific to the Town of Wakefield, please visit the Greater Boston and New Hampshire Solution.

Map showing the route of the new Woburn to Wakefield transmission line.

* Click to enlarge


About This Project

  • Route length: Approximately 8.5 miles
  • Line voltage: 345,000 volt (345-kilovolt [kV]) underground transmission line)
  • Siting review by: EFSB

When Is The Work Being Done?

  • Start of construction: 2018
  • Projected in-service date: April 2024

About this project

  • Route length: Approximately 8.5 miles
  • Line voltage: 345,000 volt (345-kilovolt [kV]) underground transmission line)
  • Siting review by: EFSB

Construction Updates

See construction updates.

Siting Review

The Massachusetts ESFB Petition Filing is part of the regulatory review process, as defined by Massachusetts state statutes.

On February 28, 2018, we received approval from the EFSB to construct the project. See the EFSB 15-04 Final Decision.

Community Outreach

Before starting construction in a community, we mail start of construction letters to property owners along the route. In addition, door-to door outreach is done in advance of each major construction phase to keep property owners informed.

Have Questions?

Keeping the lines of communication open is an important part of our work in your community.

For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.