Information on this page is for customers in 

{{ town-name }}

Andrew Square to Dewar Street Reliability Project

Why Are We Doing This Project?

To improve the reliability of Boston’s electric system now and into the future, a new 2.1 mile underground 115-kilovolt (kV) transmission line will connect Eversource's Andrew Square substation to the Dewar Street substation.

The project also includes improvements within the existing fence lines of our substations, to further ensure the delivery of safe, reliable power.

Where Is This Work Being Done?

The 2.1-mile transmission line will run under streets in Dorchester and South Boston, connecting our Andrew Square and Dewar Street substations.

When Is The Work Being Done?

  • Start of construction*Second Quarter 2022
  • Projected in-service date*: Fourth Quarter 2024

* Pending all necessary siting and permit approvals

Construction Updates

We are committed to keeping neighbors, businesses and community members informed on project activities during construction. The schedule may change due to weather or other unexpected circumstances.

We take every safety precaution while working in local communities, and all people working on the construction carry proper identification. 

This work is not expected to interrupt electric service to homes or businesses.

Andrew Square Substation

Week of April 15

There will be no work in Andrew Square this week.

Mary Ellen McCormack

Week of April 15

Crews will be mobilized on O’Connor Way, just outside the Mary Ellen McCormack Community, the week of April 15, to excavate for duct-bank along the bend of O'Connor Way. Work will last the duration of the week.

  • All work will be contained within a temporary work zone.
  • 'No parking' signs will be posted along O’Connor Way. There will be no parking in these spots during the stated work hours.
  • Equipment needed to complete this work includes a concrete cutting saw, jackhammers, excavators and dump trucks.
  • Thru and local traffic will not be able to access O'Connor Way. A traffic detour will be in place on Kemp Street for access to Mary Ellen McCormack.

Crews will be mobilizing on O’Callaghan Way, inside the Mary Ellen McCormack community at the corner of Old Colony Avenue, beginning the week of April 15 as early as Monday, working to excavate a duct-bank and install conduit.

  • All work will be contained within a temporary work zone on O’Callaghan Way during the daytime hours of 9:30 a.m. to 3:30 p.m. This work is expected to last the duration of the week.
  • Equipment needed to complete this work includes a concrete cutting saw, jackhammers, excavators, and dump trucks
  • There will be a partial road closure as part of this work on O’Callaghan. Thru-traffic will not be allowed to access O’Callaghan Way between the intersections of Gavin Way and Old Colony Avenue. Thru-traffic will be diverted north up the remainder of O’Callaghan Way where it can then exit the community via Logan Way. Exceptions to this detour will be made for emergencies and other important vehicles.
  • There will be 'No parking' signs posted along O’Callaghan Way the length of the work zone. There will be no parking allowed in these spots during daytime work hours.
  • Police details have been requested to assist with traffic management during the use of the construction work zone and traffic detour

Morissey Boulevard

Week of April 15

There will be no work on Morrissey Boulevard this week.

Savin Hill

Week of April 15

Crews will be conducting drilling activities in preparation for jack and bore work.

  • All work will be contained within the Springdale Street temporary work zone
  • This work will involve the use of a drill and generators. This equipment will produce some noise during work hours when in use

    Crews will be mobilizing on Old Colony Terrace the week of April 15. Crews will be working to excavate for duct-bank and install conduit.

    • All work will be contained within the Old Colony Terrace temporary work zone, which will extend the length of the road.
    • Equipment needed to complete this work includes a concrete cutting saw, jackhammers, excavators, and dump trucks.
    • Old Colony Terrace will become one-way alternating as our crews occupy the outbound lane. 
    • Police details have been requested to assist with traffic management 

    Dewar Street Substation

    Week of April 15

    Crews will be excavating and conducting survey work within the substation footprint in preparation for an ongoing control house upgrade.

    This work will include the use of excavators, concrete cutting saws, and jackhammers.

    Traffic Management Plans

    Working in consultation with town and state officials, including the Massachusetts Department of Transportation, we developed a traffic management plan (TMP) for each section of the project.

    The TMPs include a detailed site plan, hours of construction and area-specific traffic controls.

    All TMPs are subject to change and may be updated often.

    Siting Review

    We filed a petition with the Massachusetts EFSB for approval to construct and operate the new 115-kV transmission line.

    The petition filing is part of the regulatory review process, as defined by Massachusetts state statutes.

    On March 1, 2019, we submitted the following Siting Petition to the EFSB:

    The EFSB held a Public Comment Hearing on June 26, 2019, in Boston, where individuals and groups affected by the initial petition were given the opportunity to voice feedback to the Siting Board.

    The Siting Board conducted a remote Siting Board meeting using Zoom on June 30, 2021, at 1 p.m. to listen to comments and vote on whether to approve, approve with conditions or reject the project.

    The Siting Board's Final Decision to approve the project was issued on July 2, 2021.

    Community Outreach

    We're committed to engaging city officials, residents, businesses, community groups and other stakeholders about project activities through municipal briefings, mailings, virtual meetings and door-to-door outreach, while adhering to COVID-19 social distancing and other related health and safety guidelines.

    Sign up for weekly updates here.

    Have Questions?

    Keeping the lines of communication open is an important part of our work in your community.

    For more information about this project, please call the project information hotline at 1-833-836-0302 or email ProjectInfoMA@eversource.com.