EFFECTIVE: December 1, 2020 through April 15, 2021

Please be advised that EVERSOURCE will implement a winter construction moratorium affecting all underground sub developments (subdivisions), underground service changes and underground service relocations.

If you have pending jobs of these types, all prerequisites (contribution, easement, inspection, etc.) need to be completed by November 1, 2020. At that time, EVERSOURCE will make every effort to schedule the start or work within three weeks, depending on the scope of required work and the weather.

REMINDER - When submitting a request for sub developments, Eversource requires an eight (8) week notice along with approved Town or City plans.