Net Metering Program Capacity Information

On June 23, 2017, the NH Public Utilities Commission issued Order No. 26,029 (DE 16-576) that modified certain terms and conditions of the net metering program, including the removal of the limitation on the amount of generating capacity eligible for the new tariff. 

The table below provides information on the renewable generation projects in our service territory that are already operating in the net metering program and those that have been allocated capacity in the program but are not yet operational.  

Eversource determines which projects have reserved capacity in the program based on procedures developed during N.H. Public Utilities Commission proceeding (Docket No. DE 15-271).

Projects identified as participating in either the “Standard” or “Interim” tariff are those that received an allocation into the program prior to September 1, 2017.  Projects identified as part of the “Alternative” tariff are subject to the order issued on June 23, 2017.  Consult the Eversource tariff for additional details.

The tables below will be updated on a regular basis.

Standard or Interim Tariff
Project Category # of Projects Total Capacity (kW)
Small Projects
On-Line 5,447 46,628
In Progress 81 1,179
Total Allocated 5,528 47,807
 
Large Projects
On-Line 57 21,298
In Progress 2 1,596
Total Allocated 59 22,894
Alternate Tariff
Project Category # of Projects Total Capacity (kW)
Small Projects
On-Line 628 5,989
In Progress 216 3,231
Total Allocated 844 9,220
 
Large Projects
On-Line 8 2,529
In Progress 19 15,544
Total Allocated 27 15,073

(Data current as of February 7, 2019)