Why Are We Doing This Project?
We determined after an extensive study that integration of additional clean energy into the electrical grid in the Plymouth area requires upgrades to our West Pond Substation. This project will support interconnection of new renewable resources and improve reliability.
This work is part of a larger initiative focused on electric system enhancements to maintain reliability and enable distributed energy resource (DER) facilities to safely interconnect and operate.
Where Is This Work Being Done?
West Pond Substation is located off Federal Furnace Road in Plymouth. Upgrades to the substation include:
- Replacing two existing transformers
- Installing one new transformer
- Installing new switchgear, ring bus, capacitor banks, circuit breaker and control enclosure
- Expanding the substation to accommodate new equipment
- Relocating transmission line structures to accommodate substation expansion
- Connecting a new distribution circuit
When Is The Work Being Done?
- Proposed start of construction: Q3 2026*
- Estimated in-service date: Q3 2028
*Subject to change, pending necessary approvals
About this project
- Location: Federal Furnace Road, Plymouth
- Expansion area: 1.7 acres
- Siting review by: Energy Facilities Siting Board (EFSB)
For more information, download a project fact sheet (PDF).
Siting Review
Dates
- Petition filing with EFSB: February 2025
- EFSB public hearing: Pending
- Petition decision from EFSB: Pending
Documents
Visit the EFSB website for project filing information.
Community Outreach
We are engaging town and city officials, residents, businesses, community groups and other stakeholders via municipal briefings, open houses, mailings and meetings to answer questions and listen to concerns. We will keep you informed as the proposed project proceeds through the permitting process.
Upcoming opportunity
Join us at our open house and informational meeting to learn more about the project and share feedback.
Tuesday, May 13 from 5 - 7 p.m.
Plymouth American Legion, 199 Federal Furnace Road, Plymouth
Have Questions?
Keeping the lines of communication open is an important part of our work in your community. We welcome input from the community.
For more information about this project, please call the project information hotline at 833-836-0302 or email ProjectInfoMA@eversource.com.
Perguntas? Traduções? Envie um e-mail para a Eversource pelo endereço ProjectInfoMA@eversource.com ou ligue para 833-836-0302.
¿Tiene preguntas? ¿Traducciones? Envíe un correo electrónico a Eversource a ProjectInfoMA@eversource.com o llame al 833-836-0302.