NORWALK BRIDGE TRANSMISSION RELOCATION PROJECT

As part of the Connecticut Department of Transportation’s (CDOT) rebuilding of the Walk Bridge, Eversource must relocate and energize two electric lines that span the top of the bridge in Norwalk, Conn.

CDOT has announced plans to rebuild the Walk Bridge over the Norwalk River, ensuring continued railroad operation along the vital Northeast rail corridor.

To assist with CDOT’s plans, Eversource will first need to move two overhead lines currently following that corridor – allowing CDOT to begin its rebuilding project. This work is necessary to help keep the power flowing in Norwalk.

Project route for the Norwalk Bridge Transmission Relocation Project.

* Click to Enlarge

Proposed Route

Beginning in 2016, Eversource has worked with Norwalk officials, CDOT, and other stakeholders to develop a route that meets all required electrical reliability standards; limits environmental and community impacts; and can be built at a reasonable cost. Several potential routes for the relocation of the lines were reviewed.

The proposed route shown in the map has the two existing lines exiting the railroad corridor at the Norwalk Police Department and transitioning to underground cable beneath the Police Station parking lot and Elizabeth Street. From Water Street, we would place the lines under the Norwalk River; then the lines would continue underground in Veteran’s Memorial Park, in the area of the park entrance off Fort Point Street.

The cables would continue beneath Fort Point Street, where they would reconnect to the rail corridor in the vicinity of the Fort Point Bridge.

In keeping with the Veteran’s Memorial Park long-term development plan, Eversource intends to realign the Fort Point Street entrance with Goldstein Place, as part of the project’s restoration process.

Project Facts:

  • Route length: Approximately 0.75 miles
  • Line voltage: 115,000 volt (115-kV) underground transmission lines
  • Siting review: Connecticut Siting Council
  • Environmental permitting: Connecticut Department of Energy & Environmental Protection (CT DEEP) and U.S. Army Corps of Engineers

Estimated Schedule:

  • Public open house: November 13, 2018
  • File petition with the Connecticut Siting Council: Fourth Quarter 2018
  • File environmental permits with CT DEEP: Fourth Quarter 2018
  • Begin construction: Second Quarter 2019
  • Complete construction: Second Quarter 2020
  • Complete restoration: Third Quarter 2020

Public Open House

Eversource held an Open House on November 13, 2018, at the Norwalk City Hall Community Room to share information about the Norwalk Bridge Transmission Relocation Project. The Open House gave residents and businesses an opportunity to learn more about the project, ask questions and provide feedback.

Communications & Public Outreach

At Eversource, we’re pleased to serve the neighborhoods where we work and live. Beginning with municipal briefings and community outreach efforts related to the Norwalk Bridge Transmission Relocation Project, we have made a concerted effort to engage town officials, residents, businesses and other stakeholders to inform, answer questions, and listen to concerns about the project.

As the proposed project proceeds through the siting and permitting process, we will continue to keep you informed.

Contact Information

For more information, send an email to TransmissionInfo@eversource.com or call 800-793-2202.