Information on this page is for customers in 

{{ town-name }}

Geothermal Pilot Project in Framingham

Why Are We Doing This Project? 

We're committed to delivering New England's vision of a clean energy future and determining if networked geothermal systems are a viable option to affordably heat and cool homes and businesses.

A geothermal system uses water, wells, piping and pumps to pull the earth's heat out of the ground to warm buildings in winter and pumps heat from buildings back into the ground in summer to cool them.

It is renewable energy that comes from the sun's rays and temperatures produced in the earth's core. This energy can be used to heat and cool indoor spaces and produce hot water in conjunction with geothermal heat pumps.

Where Is The Work Being Done

The route is a neighborhood in Framingham consisting of 36 buildings – 24 residential and five commercial – for a total of 125 customer accounts. The technology may be expanded elsewhere based on the outcome of the pilot.

Learn more about the program and what participating customers receive. 

Watch our virtual tour of where we’ll be working in the neighborhood that will host this first-of-its-kind networked geothermal project.

What Work Will Be Done?

There will be three parallel stages:

  1. Drill borefields
  2. Install main in the street/install service "Ts" for individual homes/buildings
  3. Work in customers' homes.

Each is not dependent on the other, but all three must be complete prior to starting up the network.

When Is The Work Being Done?

  • Project design - Complete
  • Electrical design (best plan for powering the networked system) - Complete
  • Requesting proposals for construction work - Complete
  • Working with City of Framingham on permitting - Complete
  • Test borehole drilling, thermal capacity (test results determined viability) - Complete
  • Main and service pipe installation - Complete
  • Borefield drilling at three locations along the route - Complete
  • In-home equipment conversion work - Estimated completion Summer 2024

Construction Update

March 2024

Work on the Farley Lot pump house is progressing well. The prefabricated brick building was flown in by a crane and installed on the concrete foundation. Additionally, pipes have been installed to connect the south borefield to the pump house. During this work, our project partners at the Home Energy Efficiency Team installed fiber optic cables with the piping that will help record system function data once the testing period begins.

Crews will now focus on the installation of the equipment and mechanicals inside the pump house that will run the main borefield beneath parking lot and the geothermal system powering the Framingham Public School building

On Rose Kennedy Lane, construction work continues for the installation of heat exchanger vaults, headers, and electrical power to the satellite borefield on the Framingham Housing Authority property.

As excavation work wraps up, our team will work with contractors to coordinate sidewalk and street restoration.

Past updates:

2024 Construction Updates

February 2024

The borehole drilling has been completed. In total, 88 boreholes (averaging 600 to700 feet deep) were drilled across three locations: the Farley Lot, the fire station, and Rose Kennedy Lane. Over the next few weeks, loop piping will be installed within each hole. 

Construction has begun on the pump house in the Farley Lot, which will house the mechanical equipment needed to properly run the Farley Building and the main borefield beneath the parking lot. The structure is located at the back of the parking lot and will have a footprint of 62’L x 12’W x 11’H.

At the fire station, headers, vaults, and all lateral piping that will connect to the borefield piping under that parking lot has been installed. The parking lot is now being backfilled to return it to the fire department for parking availability. 

The Framingham Housing Authority property has remained a busy construction zone. The crew on Rose Kennedy Lane completed drilling work in mid-February and is now tying in the loops, header, and pumps. Additionally, they are connecting the borefield piping to electrical power, and starting the equipment conversion work inside FHA (Framingham Housing Authority) residential apartments. On John J. Brady Lane, a second crew continues work running underground service lines to the FHA buildings. 

January 2024

Installation of all service lines to our residential customers is complete. Borehole drilling continues on the Framingham Housing Authority property on Rose Kennedy Lane and at the south end of the Farley Lot on Normandy Road. We expect to have all drilling complete by mid-February. At the fire station on Concord Street, crews are in the process of installing laterals, headers, and setting vaults. Our next major construction steps will include building up the pump house in Farley lot and beginning building conversion work. 

2023 Construction Updates

December 2023

Service pipe installations are approximately 70% complete; we expect to continue this work through January. Bore field drilling at the fire station on Concord Street and at the north platform in Farley Lot on Normandy Road have been completed. Drilling has begun at the south platform in Farley lot and continues on Rose Kennedy Lane. Additionally, work has begun on the foundation and retaining wall for the pump house in the back of Farley Lot. 

November 2023

Our team has completed main pipe installation, connecting our pilot neighborhood in an underground loop. Borehole drilling at the fire station on Concord Street is nearly complete; next steps include restoring their parking lot/driveway. Drilling on Rose Kennedy Lane and in the Farley Lot on Normandy Road is expected to be complete before the end of the year. Simultaneously, we have begun installing service lines to businesses and homes along the route. Service line and in-home equipment installation will be our focus through the end of December.

October 2023

Main pipe installation is nearly complete. Work on Concord Street is finished. We have now made the loop connection between Concord St. and Lindbergh Road, (where the work began in June). Our final main installation tasks will be connecting Hampshire Road and Prindiville Ave., as well as installing main on John J. Brady Drive for the Framingham Housing Authority (FHA) connection. Main installation work is expected to be 100% complete by early November. Our next steps will include filling the loop piping with fluid and pressure testing the system, as well as installing service piping to customer homes and businesses. Borehole drilling continues and is making good progress at Farley Lot at MassBay Community College and the fire station on Concord Street. Our team will be bringing in a third rig to begin drilling on Rose Kennedy Lane within the FHA complex.

September 2023

We have completed approximately 70% of main pipe installation on our pilot route and are currently working on installation on Berkshire Road, Rose Kennedy Lane, and Concord Street. Borehole drilling continues at both Farley Lot (MassBay Community College on Normandy Road) and the Framingham fire station on Concord Street. Drilling is expected to continue through November. Pre-construction customer home visits have begun. We expect to begin scheduling in-home construction/system conversion in the coming weeks. 

August 2023

Main installation in the streets along the pilot route has surpassed 50% completion. Installation on Concord Street will start soon between Normandy Road and the fire station. Due to its heavy traffic pattern, drivers should expect delays on Concord St. while construction is under way in the area. Drilling for the borefields at the fire station on Concord Street and Farley Lot on Normandy Road has begun. About 90 boreholes, in total, will be drilled 600+ feet vertically to circulate the Earth's consistent temperature throughout the pilot neighborhood. We expect to complete the loop installation and borefields in October. 

July 2023

Main installation continues along the pilot route. Prep and grading of the Farley Lot at MassBay Community College will begin this month. We expect to begin borehole drilling in the parking lot in early August and complete the drilling work before September. A dedicated second crew will be working on Concord Street due to its busy traffic pattern.

June 2023

Construction for main pipe installation began. The first street completed was Lindbergh Road; we will continue installing main along the pilot route side streets throughout July.

May 2023

RH White Construction has been named as the contractor for the project.

Eversource and RH White have a strong history of working together on complex projects across multiple business areas.

Their extensive experience with plastic pipe installations will help to ensure the project is completed efficiently and to the highest quality

 

2022 Construction Updates

September 2022

Test boreholes were drilled in three locations along the pilot route. These tests helped us determine how much heat we can put in and take out of the ground with our networked system and confirmed each location was viable for full construction drilling.

Community Outreach

We're committed to engaging municipal officials, residents, businesses, community groups and neighbors about upcoming project activities.

Our efforts have included municipal briefings, direct mailings, on-site and virtual meetings, door-to-door outreach, and participation in community events. You can read more updates in the most recent geothermal email.

Featured Outreach: Customer Team Updates Participants After Summer of Construction Progress

A meeting

Our customer team hosted a third meeting for pilot participants to provide them updates on construction and what to expect in the next phase of the project, which will include finishing borehole drilling at Farley Lot, the fire station, and on the FHA property, and the installation of service lines and in-house equipment.

Past community outreach:

2023 Community Outreach

  • Webinar on October 18, 2023 - Our Clean Technologies team gives an update on the pilot progress in Framingham, MA: Construction milestones we hit this summer, lessons learned so far, and a timeline of upcoming in-home customer work ahead of system turn-on. We also bring you on a virtual tour of our pilot neighborhood. Watch a recording of the webinar.
  • Tent Sessions - Our Community Partner and Customer Team held open house informational sessions under a tent outside The Corner Cabinet shop on Concord Street every Wednesday from July to October. Members of the public were encouraged to stop by with any questions regarding the pilot.
  • Turtle Tunnels installed and fencing relocated in June 2023 – As part of our construction preparation, our team was required to install a silt fence near the construction zone to mitigate any environmental impact. However, shortly after install, neighbors told us the fence was hindering the movement of local wildlife – especially turtles coming out of Gleason Pond to lay eggs. With permission from the local conservation commission, we made adjustments to the fencing including building a ‘turtle tunnel’. Neighbors in the area tell us the tunnel is working as intended.
  • Customer Pilot Preview Meeting at Framingham Housing Authority on June 24 – Our team provided participating customers with project updates including highlights from the groundbreaking event, details about upcoming in-home visits, our recent efforts to mitigate construction impact on local wildlife, and introduced them to their dedicated Eversource Community Partner. 
  • Pilot Groundbreaking event on June 12 – We hosted state and local leaders, along with clean energy partners at MassBay Community College in Framingham for the groundbreaking of our geothermal pilot. The event marked the start of construction on this innovative project. Watch the full livestream event on Facebook.
  • Introduce a Girl to Engineering and Science at Fuller Middle School on March 2, 2023 - We partnered with the Fuller Middle School in Framingham to host a one- day program designed to encourage girls to explore the areas of engineering and science, and to help address the gender gap in the STEM fields.
  • Webinar on April 5, 2023 - Watch a recording of the webinar to hear the latest on the geothermal pilot.

2022 Community Updates

  • Customer Meeting at Fuller Middle School in Framingham on April 13, 2022 - Information session where we connected with potential pilot participants who own homes or businesses along our proposed project routes.
  • Westborough Energy Fair at Mill Pond School on April 30, 2022 - We engaged with students and community members as enthusiastic about renewable energy technology as we are.
  • Framingham "Cooler Communities" event at Harmony Grove Elementary School on May 21, 2022 - We showed fourth graders that it can be "cool" to be involved in energy, especially when talking about home heating and cooling.
  • Framingham Earth Day Festival at Framingham Centre Common on April 23, 2022 - We met with and fielded questions from fair attendees interested in knowing more about the geothermal pilot project Eversource is building in their community.

Webinars:

Have questions about the geothermal pilot?

If you have questions about the pilot or would like to receive regular updates, please email geothermal@eversource.com.