Skip to Main Content Skip to Sitemap

majorprojects

WOBURN TO WAKEFIELD LINE PROJECT

To improve reliability and address the growing need for electricity, Eversource is preparing to construct its portion of the Woburn to Wakefield Line Project.

At Eversource, we're always working to serve you better. This project includes a new 345-kilovolt (kV) underground transmission line that will connect Eversource’s Woburn Substation in Woburn and National Grid’s Wakefield Junction Substation in Wakefield, Mass.

The line will extend approximately 8.5 miles between two existing substations, passing through Woburn, Winchester, Stoneham, and Wakefield. The project also includes improvements within the existing fence lines of the Woburn and Wakefield substations.

Eversource will be constructing the new line from the Woburn Substation through Woburn, Winchester and Stoneham to the Wakefield border. For more information specific to the Town of Wakefield, please visit National Grid's website.

Map showing the route of the new Woburn to Wakefield transmission line.

* Click to Enlarge

Project Facts:

  • Route Length: Approximately 8.5 miles
  • Towns: Woburn, Winchester, Stoneham, and Wakefield, Mass.
  • Line Voltage: 345,000 volt (345-kilovolt [kV]) underground transmission line)
  • Siting Review By: Energy Facilities Siting Board (EFSB)
  • Filed Siting Petition with the EFSB: September 25, 2015
  • Petition approved by the EFSB: February 28, 2018

Estimated Timetable (subject to change):

  • Start of construction (pending all necessary permit approvals): Second Quarter 2020
  • Estimated in-service date: Mid-2021

Energy Facilities Siting Board

For an electric transmission line project, such as the Woburn to Wakefield Line Project, the Massachusetts Energy Facilities Siting Board (EFSB) Petition Filing is part of the regulatory review process, as defined by Massachusetts state statutes.

On February 28, 2018, Eversource received approval from the EFSB to construct the Woburn to Wakefield Line Project. See the EFSB 15-04 Final Decision.

Traffic Management Plans

Working in consultation with town officials, Eversource is developing Traffic Management Plans (TMPs) for the construction of the Woburn to Wakefield Line Project.

The TMPs include, among other things, conditions specific to routing by the EFSB in its decision, a site plan showing underground line location, hours of construction, and area-specific traffic controls.

Please note, TMPs are subject to change and may be updated.

Construction Updates

Eversource is committed to keeping neighbors, businesses and community members up-to-date on project activities during construction.

Construction will begin in the second quarter of 2020 and work is not expected to interrupt electric service to homes or businesses.

Construction activity is ongoing within public streets at the following location:

  • Main Street between William Street and Elm Street 

An alternate traffic pattern on Main Street will be necessary during work hours. Steel road plates will be used to temporarily, safely secure the area at the end of each day.

Pedestrian detours and parking restrictions will be necessary for the duration of the work. Parking restrictions will be clearly posted in advance.

Construction activity at these locations will occur between 7 a.m. and 3:30 p.m., Monday through Friday.

Pre-construction survey activity, including utility mark-outs and test pits (areas where we open the pavement to locate existing underground utilities), will continue within public streets during the week of June 1.

Owners of property along this project who have questions are encouraged to contact the Eversource project hotline at 1-800-793-2202 or send an email to ProjectInfo@eversource.com. A field outreach representative will respond to your inquiry via phone or email.

 

For information specific to Wakefield, please visit National Grid's website.

 

 No construction at this time. 

 

During the week of June 1, crews will begin working on Washington Street between Erie Street and Ran Drive. Crews will install a new, pre-fabricated concrete vault with the use of a crane. An alternate traffic pattern on Washington Street will be necessary during work hours. Steel road plates will be used to temporarily, safely secure the area at the end of each day.

Pre-construction survey activity, including utility mark-outs and test pits (areas where we open the pavement to locate existing underground utilities), will continue within public streets during the week of June 1.

Owners of property along this project who have questions are encouraged to contact the Eversource project hotline at 1-800-793-2202 or send an email to ProjectInfo@eversource.com. A field outreach representative will respond to your inquiry via phone or email.

 

COMMUNITY OUTREACH

Before starting construction in a community, we will mail start of construction letters to property owners along the route. Door-to-door outreach efforts for the project have been temporarily suspended due to COVID-19 health and safety concerns. This effort will resume when appropriate.

CONTACT INFORMATION

For more information about the Woburn to Wakefield Line Project, send an email to ProjectInfo@eversource.com or call 800-793-2202.