Skip to Main Content Skip to Sitemap

majorprojects

Putnam Avenue Substation Project

With the demand for electricity growing in Cambridge, Eversource is installing additional equipment at its existing Putnam Avenue Substation to enhance the electric system and continue to reliably deliver electricity to its customers.

As part of our everyday effort to deliver reliable energy to our customers, Eversource has designed the Putnam Avenue Substation Project to improve the reliability of the electric system serving Cambridge, Mass. A strong electrical grid is vital to the safety, security and economic prosperity of the region.

A new transformer and associated equipment will be added to the existing Eversource-owned substation property. An enclosure will be built around the transformer to help reduce sound and protect the equipment. Landscaping improvements and a new decorative fence will also be installed as part of this project, along with improvements to the local distribution system.

map-putnam

Important Update on COVID-19 and Essential Work  

On Tuesday, March 24, 2020, the Cambridge Inspectional Services Department (ISD) issued a letter to Cambridgeport neighborhood residents stating that construction activity at the Putnam Avenue Substation had been deemed essential in order to meet a summer in-service date to help meet peak load demands and prevent system overloads.

A copy of the Cambridge ISD letter is available below:

As we carry out this work to ensure our customers and communities have the safe, reliable energy service they need, we continue to do so with a focus on social distancing, hygiene, and other best practices to safeguard health and avoid the spread of COVID-19. Please visit Eversource’s COVID-19 informational page for details about Eversource’s policies and protocols related to COVID-19.

Cambridge Board of Zoning Appeals

As a part of preparing to install this new equipment at our existing substation site, Eversource submitted a special permit application to the Cambridge Board of Zoning Appeals (BZA). The application for expanded use was approved on September 12, 2019. See the BZA's decision

Project Facts:

  • Putnam Avenue Substation Project: New transformer and associated equipment installed at the Putnam Avenue Substation in Cambridge. 
  • City: Cambridge, Mass.
  • Board of Zoning Appeals approval: September 12, 2019.
  • Building Permit: A building permit was issued by the City of Cambridge Inspectional Services on December 26, 2019.

Estimated Timetable (subject to change):

  • Equipment installation at substation: First and Second Quarter 2020
  • Landscaping and fence improvements: Third and Fourth Quarter 2020
  • In-service date: Fall 2020

About The Project Site

The substation property is separated by a fence, and the enhancements will take place in the area that currently has no substation facilities. 

Plans to enhance the site aesthetics include: 

  • Upgrading the fence around the station so it will be complementary to the surrounding area. 
  • Replacing the existing dirt base with level gravel. 
  • New plantings to help screen equipment and provide visual interest throughout the seasons. 

Once the project is complete, stored equipment and other construction materials will be removed. 

Community Outreach

Owners of property next to the substation and other nearby residents will receive regular updates on construction, including scheduled milestones and advance notice of deliveries or other notable events.

All persons working on the project carry proper identification; and we always make safety a priority in all the work we do.

Putnam Avenue Start of Construction Letter

Construction Updates

Eversource is committed to updating neighbors, business and community members about project activities during construction. These substation enhancements are not expected to interrupt electric service to homes or businesses.

This project website will be regularly updated, reflecting locations where crews will be working and the construction activities taking place. Please keep in mind that the construction schedule is subject to change and may be impacted by weather or unexpected circumstances. 

Crews working for Eversource have received a tool truck permit from the City of Cambridge to reserve parking spots for construction vehicles in front of the project site on Putnam Avenue. These spaces are reserved for construction vehicles from 7 a.m. to 6 p.m. Monday through Friday and on Saturday between 9 a.m. and 6 p.m.

During the week of July 13, crews will work to connect new equipment with the distribution system serving Cambridge. This phase of work will require crews to work in the street and sidewalk on Putnam Avenue and may necessitate pedestrian detours and roadway lane restrictions which will clearly be posted.

This work will require a crane to remain on site and operate during work hours.

In the coming weeks, crews will complete the following construction activity:

  • Acoustic sound wall panels will be installed on the steel frame.
    • This work will require a crane to remain on site and operate during work hours.
  • Underground and above ground cable will be installed to connect new and existing equipment.
  • Pruning of overhanging vegetation.
  • Installation of perimeter fencing.

Construction activity at the site is expected to be complete by July 31, 2020 with additional distribution work, final restoration (fencing, landscaping, crushed stone) occurring through fall 2020.

Parking spots on Putnam Avenue reserved for Eversource/McCourt will be needed for construction vehicles from 8 a.m. - 4 p.m. Monday through Friday. If residents are using these spots for overnight parking, please have cars moved by 8 a.m. on weekdays. 

General work hours are 7 a.m. to 6 p.m. Monday through Friday and on Saturday between 9 a.m. and 6 p.m. Certain phases of work may require extended hours or Sunday work approval. Owners of property next to the substation will be notified in advance if these extended work hours are necessary. From time to time, portable lighting may be necessary and will be placed strategically with consideration to nearby neighbors.

Contact Information

Keeping the lines of communication open is an important part of our work in your community. For more information about the project, send an email to ProjectInfo@eversource.com or call 800-793-2202.