Mystic to Woburn Line Project

To improve reliability and address growing need for electricity identified by ISO-NE, New England’s power grid manager, Eversource is preparing to construct the Mystic to Woburn Line Project.

The project includes a new 115-kilovolt (kV) underground transmission line that will connect the Mystic substation in Everett, MA, and the Woburn substation. The line will extend approximately 8 miles between the two substations and will pass through Everett, Boston (Charlestown), Somerville, Medford, Winchester, and Woburn.

The project also includes improvements within the existing fence lines of the Woburn and Mystic substations. Information about the project is also available in Spanish, Portuguese and Haitian Creole.

Map of the project route.

* Click to Enlarge

Project Facts:

  • Route Length: Approximately 8  miles
  • Towns: Everett, Boston (Charlestown), Somerville, Medford, Winchester, and Woburn, MA
  • Line Voltage: 115,000 volt (115-kV) underground transmission line
  • Siting Review By: Energy Facilities Siting Board (EFSB)

Estimated Timetable (Subject to Change):

  • File Environmental Notification Form for review under the Massachusetts Environmental Policy Act (MEPA): April 30, 2015
  • File Siting Petition with the EFSB: ​​May 20, 2015
  • Petition approval by the EFSB: March 9, 2017
  • Start of ​construction: ​​July 2017
  • Estimated ​In-​Service ​Date: ​2018

Energy facilities Siting Board

For an electric transmission line project, such as the Mystic to Woburn Line Project, the Massachusetts Energy Facilities Siting Board (EFSB) Petition Filing is part of the siting regulatory view process, as defined by Massachusetts state statutes. On March 9, 2017, Eversource received approval from the EFSB to construct the Mystic to Woburn Line Project.

Traffic Management Plans

Working in consultation with town and state officials, including the Mass. Department of Transportation, Eversource has developed a Traffic Management Plan (TMP) for each section of the Mystic-Woburn Line Project.

The TMPs include conditions specific to routing by the EFSB in its decision, a detailed site plan showing underground line location, hours of construction, area-specific traffic controls and more.

Some of the TMPs below are large in size and might take some time to load or download.

Please note, TMPs are subject to change and may be updated often.

Construction Updates

Eversource is committed to updating neighbors, businesses and all community members about project activities, especially during construction.

The sections below feature weekly construction updates for each town. Please note that the project work is not expected to interrupt electric service to homes or businesses.

Construction will begin in the third quarter of 2017, once we receive all necessary permits.

Construction started at the Mystic Substation in late July 2017. All construction activities will be inside the fence at the substation. No substation expansion is planned.

Construction will begin in the third quarter of 2017, once we receive all necessary permits.

Starting the week of September 18, Crews will be performing land survey work, installing underground concrete vaults, and digging trenches on Mystic Avenue (between Memorial Road and Grant Street) in Somerville. Work in this area is expected to continue through November.

Construction will begin in the third quarter of 2017, once we receive all necessary permits.

Construction has begun at the Woburn Substation. Excavating and trenching on the right of way on Pond Street in Woburn will begin in ​October 2017.

CONTACT INFORMATION

For more information about the Mystic to Woburn Line Project, send an email to TransmissionInfo@eversource.com or call 800-793-2202.