Massachusetts Application to Connect

In this section you will find information pertaining to the safe interconnection of generators to the Eversource power system.

Such interconnections include photovoltaic arrays (solar panels), wind turbines, cogeneration units and micro turbines, to name a few.  All regulations and fees have been filed and approved by the Massachusetts Department of Public Utilities (DPU).

Interconnection Application Options

EMA Criteria State Guideline App. Forms App. Fee
Simplified Standard Simplified N/A
Simplified Network Standard Simplified

3 kW $100
> 3 kW $300

Pre-Application
(Projects > 500 kW)
Standard Pre-App. N/A
Expedited/Standard
(Projects not meeting the Simplified criteria)
Standard Exp./Std. $4.50/kW 1
WMA Criteria State Guideline App. Forms App. Fee
Simplified Standard Simplified N/A
Simplified Network Standard Simplified

3 kW $100
> 3 kW $300

Pre-Application
(Projects > 500 kW)
Standard Pre-App. N/A
Expedited/Standard
(Projects not meeting the Simplified criteria)
Standard Exp./Std. $4.50/kW 1

Minimum $300; Maximum $7,500

Application Descriptions

Simplified
You will follow the simplified process and use the Simplified application if you intend to install:

  • A single phase Listed inverter-based system that is 15 kW or less on a single phase service fed from a radial circuit, or
  • A three phase Listed inverter-based system that is 25 kW or less on a three phase service fed from a radial circuit, or 

Simplified (Network)
You will follow the simplified process and use the Simplified application if you intend to install:

  • A Listed inverter-based system less than 1/15th of customer’s minimum load and fed from a spot network, or
  • A Listed inverter-based system that is 15 kW or less and less than 1/15th of the customer’s minimum load and fed from an area network

Pre-Application Request
Customers proposing to install a generation facility 500 kW or greater are required to submit a Pre-Application request.  

Prior to submitting either an Expedited or Standard Process application, all customers with facilities that are 500 kW or greater need to complete a pre-application report online or request one from Eversource. This report is optional for facilities that are less than 500 kW. There is no fee for either report.

Expedited/Standard
You will follow the expedited process and use the Expedited/Standard application if you intend to install:

  • A system that is greater than 15 kW single phase, or greater than 25 kW three phase, or
  • Your system configuration does not correspond with the service configuration (such as using single phase inverters on a three phase service); and
  • Your proposed generation equipment must meet IEEE 1547.1 standards;
  • You must be on a radial distribution circuit;
  • A non-inverter based generator, co-generator, wind, hydro or other facility.

Please note: If your project is 1 megawatt (MW) or larger, ISO-New England approval is also required. This will add approximately two to six months to the application process.

Eversource will review each application and contact the applicant regarding any engineering evaluations that must be performed in order to permit the interconnection. In some simple cases (e.g. most residential solar systems), no studies are required.

For other projects, one or more detailed engineering reviews will be required to evaluate the impact of the generation source on the Eversource distribution system and, possibly, the transmission system.

Net Metering

If you are installing distributed generation (e.g., solar panels), or already have a generator, you may be eligible for net metering, a method of measuring the energy consumed and produced by a customer’s generating facility. If you are a customer applying for electrical interconnection, and you want to be considered for net metering, you must also submit the net metering application.

Important Documents or Links

​Contact Eversource

Eastern Massachusetts Western Massachusetts

Applications, fees and documents can be mailed to: 

Eversource Energy
Attention: Eversource EM DG
​247 Station Drive
Westwood, MA 02090

Simplified Apps: 781-441-8285
All Other Apps: 781-441-8196

Application and documentation can me emailed to:

emdg@eversource.com

 

 

 

 

 

 

 

 

Applications, fees and documents can be mailed to:

Eversource Energy
Attention: Eversource WM DG
55 Russell Street
Hadley, MA 01035-9455

413-787-1087

Application and documentation can me emailed to: 

wmdg@eversource.com